- Factory
- Road
- Site
- Set
- Connect
- Building
A modular building on its site: the grade beam, piers and water, power and sewer services are prepared while a tower crane stands ready; twelve factory-built modules are set onto the foundation and onto each other; their structural ties, plumbing stacks, electrical feeders and sprinklers are connected across every joint; and the cladding closes them into one building.Piers & grade beamWater servicePower serviceSewer serviceTower craneStructural tiesPlumbing stackElectrical feederSprinklers
A modular factory: a module is framed and serviced on the production line, and a finished module, wrapped and sized for the road, leaves on a flatbed truck.Framed & servicedLifting pointsSized for the road
- Structural ties
- Plumbing & mechanical stacks
- Electrical feeders
- Fire separations & sprinklers
Built on the line
Each module is framed, serviced and finished in the factory. Our drawings set out the structure, ductwork, piping and wiring inside every box, coordinated with the manufacturer’s production system rather than imposed on it.
- Module structure
- Services roughed in
- Factory documentation
Sized for the road
A module’s width and height are shaped by what can travel and be lifted. Transport and lifting design belong to the specialists appointed for them; we design each module to their limits and check the permanent structure against the conditions they define.
- Module dimensions
- Lifting points coordinated
- Permanent structure checked
The site, at the same time
While the modules are being built, the site is graded and serviced and the foundations go in. Civil and structural design for the site runs in parallel with the factory, which is why modular can shorten a programme.
- Foundations and anchorage
- Site servicing and grading
- Utility connections
Set
Modules are craned onto the foundation and onto each other. Their dimensions, tolerances and connection points have to agree with the drawings before the first one leaves the factory.
Trenton Ave. Housing was craned into place in April 2022 and opened that November. Trenton Ave. Housing ↗
Connect
Where the project is won or lost: the mate lines. Structural ties between modules, plumbing stacks and ducts that pass from one box to the next, electrical feeders, and fire separations and sprinklers across every joint.
- Structural ties
- Plumbing and mechanical stacks
- Electrical feeders
- Fire separations and sprinklers
One building
What remains is a building, not a set of boxes. We coordinate the documentation with the manufacturer, certifier and authorities—including the CSA A277 factory certification process—and the site inspections that follow.
253 King William Street, built with modular methods, achieved Certified Passive House Classic designation. Hamilton Passive House Modular Housing ↗